An asbestos clearance certificate is a written statement from an independent person, issued after licensed asbestos removal, confirming that no visible asbestos residue remains.
In Victoria, the person who commissions Class A or Class B asbestos removal must obtain one before the area is re-occupied. The exception is non-friable asbestos totalling 10 square metres or less.
On a DigDig demolition it's arranged as part of the job. Here's how it works.
What a clearance certificate is
After asbestos has been removed, someone has to check the work. A clearance certificate is the written record of that check. Under Victoria's Occupational Health and Safety Regulations 2017 it must state that:
- an inspection by an independent person found no visible asbestos residue remaining from the removal work, in the area where it was performed or in the area immediately surrounding it, and
- where air monitoring is required, the airborne asbestos fibre level in the area is less than 0.01 fibres per millilitre.
In plain terms: the asbestos is gone, the area has been cleaned of visible debris from the removal, and someone independent has confirmed it.
When one is required
The regulations put the responsibility on the person who commissioned the work. They must obtain a clearance certificate from an independent person on completion of Class A or Class B asbestos removal work, and before the area is re-occupied.
The two licence classes cover different material:
- Class B is non-friable asbestos, and asbestos-contaminated dust from removing it.
- Class A is friable asbestos and most other asbestos-contaminated dust, as well as Class B work.
The exception. A clearance certificate is not required if the removal consisted only of non-friable asbestos-containing material not exceeding 10 square metres in total. Anything larger, or any friable asbestos, needs one.
Who can issue it
The certificate has to come from an independent person, meaning someone independent of both the person who commissioned the work and the licensed removalist, with the knowledge, skills and experience to do the inspection. Victorian Government guidance gives an occupational hygienist as an example.
That independence is the point. The business that removed the asbestos isn't the one signing off that it was removed.
Where it fits in a demolition
On a house demolition, asbestos removal and its clearance come before the machines arrive. The order of events is:
- The licensed removalist notifies WorkSafe before work starts.
- The asbestos is removed.
- An independent person inspects and the clearance certificate is issued.
- A timber salvage crew strips anything reclaimable, about a day's work.
- The main demolition begins, usually one to three days for a single-storey house.
The full sequence, including permits and power and gas abolishment, is in how long house demolition takes.
The WorkSafe notice that comes first
Before licensed asbestos removal begins, the removalist has to notify WorkSafe. The notice period depends on the job:
| Job | Notify WorkSafe |
|---|---|
| Non-friable asbestos, 10 square metres or less | At least 24 hours before starting |
| Friable asbestos, or non-friable over 10 square metres | At least five business days before starting |
| Unexpected situations | Within 24 hours of starting |
The removalist, not the homeowner, is usually responsible for lodging this notification.
How DigDig handles asbestos
DigDig holds a WorkSafe Class B asbestos removal licence, and asbestos removal is done as part of a full demolition, not as a standalone service. The licence means a demolition doesn't have to stall waiting for a second contractor to turn up. The clearance certificate is arranged as part of the job, so it isn't something you need to organise yourself.
If you're keeping your house and only need asbestos removed, you'll need a dedicated asbestos removalist. See demolition with licensed asbestos removal for how we work, and how to check any contractor's licence.
Common questions
What is an asbestos clearance certificate?
A written statement from an independent person confirming that an inspection found no visible asbestos residue in and around the area where asbestos was removed, and, where air monitoring is required, that airborne fibres are below 0.01 fibres per millilitre.
Who has to get a clearance certificate in Victoria?
Under the Occupational Health and Safety Regulations 2017, the person who commissioned the Class A or Class B asbestos removal work must obtain the certificate from an independent person on completion of the work and before the area is re-occupied.
Is a clearance certificate always required after asbestos removal?
No. It isn't required where the removal consisted only of non-friable asbestos-containing material not exceeding 10 square metres in total. Larger removals and any friable asbestos need a certificate.
Who can issue an asbestos clearance certificate?
An independent person with the knowledge, skills and experience to carry out the inspection, independent of both the person who commissioned the work and the licensed removalist. An occupational hygienist is one example.
Does DigDig arrange the clearance certificate on a demolition?
Yes. Asbestos removal is carried out as part of a full demolition, and the clearance certificate is arranged as part of the job.